Monte Carlo schedule risk analysis of a resource-loaded project schedule.
Each iteration samples activity durations (from their distributions, or
from work and sampled resource productivity), samples which discrete risk
events occur and their impacts, and reschedules the network with the
critical path method (optionally resource-leveled; see cpm()). The
result describes the distribution of project finish and cost, how often
and how strongly each activity drives the finish, the impact of each risk,
and the uncertainty in the cost S-curve and resource usage over time.
Arguments
- x
A
"pra_schedule"object fromproject_schedule().- num_sims
Number of Monte Carlo iterations. Default 10000.
- level
Logical. Resource-level each iteration. Default
FALSE.- keep_samples
Logical. Keep the per-iteration duration, start, finish, criticality and risk-occurrence matrices. Default
FALSE.- grid_n
Number of time points for the cost S-curve and resource profiles. Default 100.
Value
An S3 object of class "sra", a list with:
- total_distribution
Simulated project finish, one per iteration.
- total_mean, total_sd
Mean and standard deviation of the finish.
- percentiles
P10, P50, P80 and P90 of the finish.
- cost_distribution
Simulated project cost, one per iteration.
- cost_percentiles
P10, P50, P80 and P90 of the cost.
- deterministic
The
cpm()result on baseline durations.- prob_deterministic
Probability of finishing no later than the deterministic finish.
- activity_stats
Data frame of per-activity results: deterministic start and finish, mean and standard deviation of duration, mean and P10/P50/P90 start and finish, criticality index, duration sensitivity, cruciality and SSI.
- risk_stats
Data frame of per-risk results: probability, simulated occurrence rate, finish impact, cost impact and rank by finish impact. Zero rows when there are no risks.
- risk_net_stats
When the schedule has a
risk_net, a data frame with one row per network node:kind("event"for nodes whose draws are all 0 or 1, otherwise"continuous"),occurrenceandmeanof its draws,finish_impactandcost_impact(mean when the event occurred minus mean when it did not; events only),finish_sensitivityandcost_sensitivity(Spearman correlation of the node with finish and cost) andrankby finish impact.NULLwithout a risk network.- time_grid
Time points used for the curves below.
- cost_curve
Data frame of cumulative cost over
time_grid:mean,p10,p50,p90.- resource_profile
Named list, one data frame per resource, of usage over
time_grid(mean,p10,p50,p90) with acapacityattribute.- samples
When
keep_samples = TRUE, a list of iteration x activity matricesduration,start,finish,critical, the iteration x risk matrixrisk_occurred, the risk-network drawsrisk_net(a data frame, orNULL), and the iteration x resource matricesproductivity_multiplierandrate_multiplier; otherwiseNULL.- leveled, num_sims, project
Settings and the input schedule.
Objects of this class have print.sra(), summary.sra() and plot.sra()
methods.
Details
Activity measures.
Criticality index: the proportion of iterations in which the activity is critical (zero total float, or on the driving path when leveled).
Duration sensitivity: Spearman rank correlation between the activity's sampled duration and the project finish.
Cruciality index: criticality index times duration sensitivity (Williams, 1992), which ranks activities by how much they actually move the finish date.
Schedule sensitivity index (SSI): criticality index times the ratio of the activity's duration standard deviation to the project finish standard deviation (PMI, 2009).
Measures based on duration spread are NA for activities whose duration
never varies.
Risk measures. For each risk, the mean finish (and cost) in iterations
where it occurred minus the mean in iterations where it did not; NA when
the risk always or never occurred.
Risk networks. When the schedule has a risk_net (see
project_schedule()), its nodes are sampled jointly with prob_net_sim()
in every iteration, so risks that share a root cause occur together, and
their risk_effects scale the productivity and cost rates of the resources
they name. Because node statistics compare iterations where an event did and
did not occur, a root cause's finish_impact includes the effects of every
risk it drives, and a risk correlated with others through a shared cause is
credited with part of their effects too.
Merge bias. Where paths converge, the finish is driven by the longest of
several uncertain paths, so the mean simulated finish usually exceeds the
deterministic finish even when every duration is symmetric. This is why a
network analysis differs from summing task durations with mcs().
Time-phasing. Each activity's cost (resource cost, fixed cost and its
share of risk costs) is spread linearly over its scheduled dates. Resource
usage is the sum of assigned units over the activities running at each
time. Both are evaluated on grid_n points from zero to the latest
simulated finish and summarized by their mean and P10, P50 and P90.
Performance. Without leveling, the critical path passes are vectorized across iterations and are fast. Leveling schedules every iteration separately with a serial schedule-generation scheme whose cost grows with the square of the number of activities, so large leveled models may need fewer iterations.
The returned object carries total_distribution, so contingency()
applies directly to schedule contingency.
References
Williams, Terry M. Criticality in stochastic networks. Journal of the Operational Research Society 43.4 (1992): 353-357.
Project Management Institute. Practice Standard for Project Risk Management. Newtown Square, PA: PMI, 2009.
Vanhoucke, Mario. Measuring time: Improving project performance using earned value management. Springer, 2009.
Examples
activities <- data.frame(id = c("A", "B", "C", "D"), duration = c(3, 5, 4, 2))
links <- data.frame(
source = c("A", "A", "B", "C"),
target = c("B", "C", "D", "D")
)
duration_dists <- list(
B = list(type = "triangular", a = 4, b = 5, c = 9),
C = list(type = "triangular", a = 3, b = 4, c = 8)
)
risks <- list(list(
id = "Rework", prob = 0.2, activities = "D",
impact = list(type = "uniform", min = 1, max = 2)
))
proj <- project_schedule(activities, links,
duration_dists = duration_dists, risks = risks
)
set.seed(42)
res <- sra(proj, num_sims = 2000)
res
#> Schedule Risk Analysis
#> Iterations: 2,000
#> Deterministic finish: 10 periods (P10)
#> Mean finish: 11.53 periods SD: 1.189
#> Finish percentiles:
#> 10% 50% 80% 90%
#> 9.995 11.470 12.550 13.100
#> Most critical activities:
#> id criticality cruciality
#> A 1.000 NA
#> D 1.000 0.487
#> B 0.728 0.521
#> C 0.272 0.080
res$activity_stats[, c("id", "criticality", "cruciality")]
#> id criticality cruciality
#> 1 A 1.0000 NA
#> 2 B 0.7275 0.5212753
#> 3 C 0.2725 0.0804491
#> 4 D 1.0000 0.4873088
contingency(res, phigh = 0.8, pbase = 0.5)
#> 80%
#> 1.08829
# A supply-chain root cause drives a labor shortage that slows the crew on
# both B and C, so one risk delays two activities through a resource.
net <- prob_net(
data.frame(id = c("SupplyChain", "Shortage")),
data.frame(source = "SupplyChain", target = "Shortage"),
list(
SupplyChain = list(type = "discrete", values = c(1, 0), probs = c(0.3, 0.7)),
Shortage = list(
type = "conditional", condition = "SupplyChain",
true_dist = list(type = "discrete", values = c(1, 0), probs = c(0.8, 0.2)),
false_dist = list(type = "discrete", values = c(1, 0), probs = c(0.1, 0.9))
)
)
)
proj_net <- project_schedule(activities, links,
duration_dists = duration_dists,
resources = data.frame(id = "crew", rate = 500),
assignments = data.frame(activity = c("B", "C"), resource = "crew", units = 1),
risk_net = net,
risk_effects = list(
list(node = "Shortage", resources = "crew", effect = "productivity",
magnitude = list(type = "triangular", a = 0.6, b = 0.8, c = 0.9)),
list(node = "SupplyChain", resources = "crew", effect = "rate",
magnitude = list(type = "uniform", min = 1.1, max = 1.3))
)
)
res_net <- sra(proj_net, num_sims = 2000)
res_net$risk_net_stats
#> id kind occurrence mean finish_impact cost_impact
#> 1 SupplyChain event 0.2995 0.2995 1.425979 2690.066
#> 2 Shortage event 0.3210 0.3210 1.958019 2794.433
#> finish_sensitivity cost_sensitivity rank
#> 1 0.4139164 0.6793854 2
#> 2 0.5851144 0.7260997 1