Computes the deterministic schedule of a project_schedule() from its
baseline durations: early and late start and finish dates, total and free
float, and the critical path. All four precedence-diagramming link types
(FS, SS, FF, SF) and lags are supported. With level = TRUE the schedule is
resource-leveled against the capacity of each capacity-limited resource.
Arguments
- x
A
"pra_schedule"object fromproject_schedule().- level
Logical. Level resources against capacity. Default
FALSE.
Value
An S3 object of class "cpm", a list with:
- activities
Data frame with one row per activity:
id,name,duration,ES,EF,LS,LF,total_float,free_floatandcritical.- finish
Project finish time.
- critical_path
Ids of critical activities in start order.
- cost
Deterministic project cost: resource cost plus fixed cost.
- leveled
Whether the schedule was resource-leveled.
- project
The input schedule.
Objects of this class have print.cpm(), summary.cpm() and plot.cpm()
methods.
Details
Forward pass. Activities are visited in topological order. An activity
starts at the latest of time zero and the constraint of each incoming link:
FS: predecessor finish + lag; SS: predecessor start + lag; FF:
predecessor finish + lag - own duration; SF: predecessor start + lag - own
duration.
Backward pass. From the project finish (the latest early finish), each activity's late finish is the earliest of the project finish and the mirror constraint of each outgoing link. Total float is late start minus early start, and an activity is critical when its total float is zero (within a small numerical tolerance). Free float is the slack before an activity delays any successor's early dates.
Resource leveling. With level = TRUE activities are scheduled by the
serial schedule-generation scheme (Kolisch, 1996): repeatedly take the
eligible activity with the smallest unconstrained late start and place it at
the earliest time that satisfies its links and keeps every capacity-limited
resource within capacity for the activity's whole duration. Float is not
meaningful once resources move dates, so late dates and floats are NA and
criticality is determined by tracing the driving path backward from the
project finish through binding links and through resource hand-offs.
References
Kelley, James E., and Morgan R. Walker. Critical-path planning and scheduling. Papers presented at the December 1-3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference (1959): 160-173.
Kolisch, Rainer. Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research 90.2 (1996): 320-333.
Examples
activities <- data.frame(id = c("A", "B", "C", "D"), duration = c(3, 5, 4, 2))
links <- data.frame(
source = c("A", "A", "B", "C"),
target = c("B", "C", "D", "D")
)
sched <- cpm(project_schedule(activities, links))
sched
#> Critical Path Method
#> Project finish: 10 periods
#> Critical path: A -> B -> D
#>
#> id duration ES EF LS LF total_float free_float critical
#> A 3 0 3 0 3 0 0 TRUE
#> B 5 3 8 3 8 0 0 TRUE
#> C 4 3 7 4 8 1 1 FALSE
#> D 2 8 10 8 10 0 0 TRUE
sched$critical_path
#> [1] "A" "B" "D"