Build a Project Schedule for Critical Path and Schedule Risk Analysis.
Source:R/schedule.R
project_schedule.RdAssembles and validates a resource-loaded project schedule: activities,
precedence links, duration uncertainty, resources with capacities and cost
rates, resource assignments, and a register of discrete risk events. The
result is the input to cpm() (deterministic critical path method) and
sra() (Monte Carlo schedule risk analysis).
Usage
project_schedule(
activities,
links = NULL,
duration_dists = NULL,
resources = NULL,
productivity_dists = NULL,
assignments = NULL,
risks = NULL,
cor_mat = NULL,
start_date = NULL,
time_unit = "periods",
risk_net = NULL,
risk_effects = NULL
)Arguments
- activities
A data frame with one row per activity and columns
id(required, unique),name(optional label, defaults toid),duration(non-negative baseline duration; may beNAfor activities whose duration comes from a distribution or work assignments) andfixed_cost(optional non-resource cost, default 0).- links
A data frame of precedence links with columns
sourceandtarget(activity ids), and optionaltype("FS","SS","FF"or"SF", case-insensitive, default"FS") andlag(default 0).NULLfor a schedule without links.- duration_dists
Optional named list of duration distributions, named by activity id.
- resources
Optional data frame with columns
id(required),capacity(positive units available,NA= unconstrained, defaultNA) andrate(non-negative cost per unit per time unit, default 0).- productivity_dists
Optional named list of productivity multiplier distributions, named by resource id. A draw of 0.8 makes that resource's work-driven activities take 1 / 0.8 = 1.25 times longer.
- assignments
Optional data frame with columns
activity,resource,units(positive units used per time unit while the activity runs) and optionalwork(positive total work;NAfor an assignment that does not drive duration).- risks
Optional list of risk events; see Details.
- cor_mat
Optional correlation matrix among the activities in
duration_dists, in the order ofnames(duration_dists)or with matching dimnames. Must be positive definite. Induced by a Gaussian copula, as inmcs().- start_date
Optional project start
Date(or a string coercible byas.Date()) used to label plot axes. Time is otherwise measured in abstracttime_units from zero; calendars are not modelled.- time_unit
Character label for the time unit, such as
"days"or"weeks". Used for labels only.- risk_net
Optional
prob_net()of root causes and risk events whose effects reach the schedule throughrisk_effects. Every node must have a distribution.- risk_effects
Optional list of effects linking
risk_netnodes to resources; see Details.
Value
An S3 object of class "pra_schedule": a list holding the
validated and normalized inputs together with the topological order and
adjacency matrix of the activity network. Objects of this class have
print.pra_schedule(), summary.pra_schedule() and plot.pra_schedule()
methods.
Details
Durations. Every activity needs exactly one duration source:
a fixed
durationinactivities;an entry in
duration_dists(itsduration, if also given, is used as the deterministic baseline; otherwise the baseline is the mode of a triangular or PERT distribution, or the mean of a normal or uniform one);work assignments (
workinassignments), in which case the activity is resource-driven: its duration is the longest ofwork / (units * productivity)across its work assignments, with productivity 1 in the deterministic baseline. A resource-driven activity cannot also have a duration distribution; uncertainty enters throughproductivity_dists.
Links. Precedence links use the precedence diagramming method: FS
(finish-to-start), SS (start-to-start), FF (finish-to-finish) and SF
(start-to-finish), each with a lag in time units, which may be negative
(a lead). Links must form a directed acyclic graph; a cycle is an error
that names the activities on it.
Resources. A resource with a finite capacity is capacity-limited and
is respected when scheduling with level = TRUE in cpm() or sra(); a
capacity of NA means unconstrained. rate is cost per unit of resource
per time unit, so an assignment costs units * rate * duration. No single
assignment may need more units than its resource's capacity.
Risks. Each risk is a list with id, prob (probability of
occurring in an iteration), activities (ids it affects), impact (a
distribution of time added to each affected activity's duration when the
risk occurs) and optionally cost_impact (a distribution of cost added when
it occurs, shared equally among the affected activities for time-phasing).
Risk networks. risk_net is a prob_net() of root causes and risk
events, sampled jointly in every sra() iteration so that risks sharing a
cause occur together. risk_effects connects its nodes to resources; one
effect can name several resources, and every activity assigned to an
affected resource feels it, so a single risk reaches many tasks. Each
effect is a list with:
node: a node id inrisk_net;resources: the resource ids it affects;effect:"productivity"(multiplies the resources' productivity, so a value of 0.8 makes their work take 1 / 0.8 = 1.25 times longer) or"rate"(multiplies their cost rate);magnitude: either a distribution specification for the multiplier, drawn once per iteration and applied whenever the node's sampled value is non-zero (for a 0/1 risk node, when the risk occurs), or the string"node", which uses the node's own sampled value as the multiplier in every iteration (for severity nodes).
A productivity multiplier slows every activity assigned to the resource.
Work-driven activities use it inside work / (units * productivity); any
other activity has its duration divided by the smallest multiplier among
its assigned resources. Baseline productivity_dists still apply only to
work-driven activities, since a duration distribution already includes
ordinary productivity variation. Multipliers from several effects on one
resource multiply together. Productivity multipliers must be positive and
rate multipliers non-negative. Risk-network effects act for the whole
project and are not applied to the deterministic baseline in cpm().
Distributions. Distribution specifications use the same format as
mcs(): a list with a type of "normal" (mean, sd), "triangular"
(a = min, b = mode, c = max), "uniform" (min, max) or "pert"
(a, b, c, the Beta-PERT distribution). Sampled durations are
truncated at zero. Productivity multipliers must use a bounded type
(triangular, uniform or PERT) with a positive minimum.
References
Damnjanovic, Ivan, and Kenneth Reinschmidt. Data analytics for engineering and construction project risk management. Cham, Switzerland: Springer, 2020.
Kolisch, Rainer. Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research 90.2 (1996): 320-333.
Examples
activities <- data.frame(
id = c("A", "B", "C", "D"),
duration = c(3, 5, 4, 2)
)
links <- data.frame(
source = c("A", "A", "B", "C"),
target = c("B", "C", "D", "D"),
type = c("FS", "SS", "FS", "FF"),
lag = c(0, 1, 0, 1)
)
duration_dists <- list(
B = list(type = "triangular", a = 4, b = 5, c = 9),
C = list(type = "pert", a = 3, b = 4, c = 7)
)
resources <- data.frame(id = "crew", capacity = 1, rate = 1000)
assignments <- data.frame(
activity = c("B", "C"), resource = "crew", units = 1
)
risks <- list(
list(
id = "Late permit", prob = 0.3, activities = "A",
impact = list(type = "uniform", min = 1, max = 3)
)
)
proj <- project_schedule(activities, links,
duration_dists = duration_dists, resources = resources,
assignments = assignments, risks = risks, time_unit = "days"
)
proj
#> Project Schedule
#> Activities: 4 Links: 4 Resources: 1 Risks: 1
#> Time unit: days
#>
#> id duration driver predecessors
#> A 3 fixed
#> B 5 distribution A
#> C 4 distribution ASS+1
#> D 2 fixed B, CFF+1