Assembles and validates a resource-loaded project schedule: activities, precedence links, duration uncertainty, resources with capacities and cost rates, resource assignments, and a register of discrete risk events. The result is the input to cpm() (deterministic critical path method) and sra() (Monte Carlo schedule risk analysis).

Usage

project_schedule(
  activities,
  links = NULL,
  duration_dists = NULL,
  resources = NULL,
  productivity_dists = NULL,
  assignments = NULL,
  risks = NULL,
  cor_mat = NULL,
  start_date = NULL,
  time_unit = "periods",
  risk_net = NULL,
  risk_effects = NULL
)

Arguments

activities

A data frame with one row per activity and columns id (required, unique), name (optional label, defaults to id), duration (non-negative baseline duration; may be NA for activities whose duration comes from a distribution or work assignments) and fixed_cost (optional non-resource cost, default 0).

A data frame of precedence links with columns source and target (activity ids), and optional type ("FS", "SS", "FF" or "SF", case-insensitive, default "FS") and lag (default 0). NULL for a schedule without links.

duration_dists

Optional named list of duration distributions, named by activity id.

resources

Optional data frame with columns id (required), capacity (positive units available, NA = unconstrained, default NA) and rate (non-negative cost per unit per time unit, default 0).

productivity_dists

Optional named list of productivity multiplier distributions, named by resource id. A draw of 0.8 makes that resource's work-driven activities take 1 / 0.8 = 1.25 times longer.

assignments

Optional data frame with columns activity, resource, units (positive units used per time unit while the activity runs) and optional work (positive total work; NA for an assignment that does not drive duration).

risks

Optional list of risk events; see Details.

cor_mat

Optional correlation matrix among the activities in duration_dists, in the order of names(duration_dists) or with matching dimnames. Must be positive definite. Induced by a Gaussian copula, as in mcs().

start_date

Optional project start Date (or a string coercible by as.Date()) used to label plot axes. Time is otherwise measured in abstract time_units from zero; calendars are not modelled.

time_unit

Character label for the time unit, such as "days" or "weeks". Used for labels only.

risk_net

Optional prob_net() of root causes and risk events whose effects reach the schedule through risk_effects. Every node must have a distribution.

risk_effects

Optional list of effects linking risk_net nodes to resources; see Details.

Value

An S3 object of class "pra_schedule": a list holding the validated and normalized inputs together with the topological order and adjacency matrix of the activity network. Objects of this class have print.pra_schedule(), summary.pra_schedule() and plot.pra_schedule() methods.

Details

Durations. Every activity needs exactly one duration source:

  • a fixed duration in activities;

  • an entry in duration_dists (its duration, if also given, is used as the deterministic baseline; otherwise the baseline is the mode of a triangular or PERT distribution, or the mean of a normal or uniform one);

  • work assignments (work in assignments), in which case the activity is resource-driven: its duration is the longest of work / (units * productivity) across its work assignments, with productivity 1 in the deterministic baseline. A resource-driven activity cannot also have a duration distribution; uncertainty enters through productivity_dists.

Links. Precedence links use the precedence diagramming method: FS (finish-to-start), SS (start-to-start), FF (finish-to-finish) and SF (start-to-finish), each with a lag in time units, which may be negative (a lead). Links must form a directed acyclic graph; a cycle is an error that names the activities on it.

Resources. A resource with a finite capacity is capacity-limited and is respected when scheduling with level = TRUE in cpm() or sra(); a capacity of NA means unconstrained. rate is cost per unit of resource per time unit, so an assignment costs units * rate * duration. No single assignment may need more units than its resource's capacity.

Risks. Each risk is a list with id, prob (probability of occurring in an iteration), activities (ids it affects), impact (a distribution of time added to each affected activity's duration when the risk occurs) and optionally cost_impact (a distribution of cost added when it occurs, shared equally among the affected activities for time-phasing).

Risk networks. risk_net is a prob_net() of root causes and risk events, sampled jointly in every sra() iteration so that risks sharing a cause occur together. risk_effects connects its nodes to resources; one effect can name several resources, and every activity assigned to an affected resource feels it, so a single risk reaches many tasks. Each effect is a list with:

  • node: a node id in risk_net;

  • resources: the resource ids it affects;

  • effect: "productivity" (multiplies the resources' productivity, so a value of 0.8 makes their work take 1 / 0.8 = 1.25 times longer) or "rate" (multiplies their cost rate);

  • magnitude: either a distribution specification for the multiplier, drawn once per iteration and applied whenever the node's sampled value is non-zero (for a 0/1 risk node, when the risk occurs), or the string "node", which uses the node's own sampled value as the multiplier in every iteration (for severity nodes).

A productivity multiplier slows every activity assigned to the resource. Work-driven activities use it inside work / (units * productivity); any other activity has its duration divided by the smallest multiplier among its assigned resources. Baseline productivity_dists still apply only to work-driven activities, since a duration distribution already includes ordinary productivity variation. Multipliers from several effects on one resource multiply together. Productivity multipliers must be positive and rate multipliers non-negative. Risk-network effects act for the whole project and are not applied to the deterministic baseline in cpm().

Distributions. Distribution specifications use the same format as mcs(): a list with a type of "normal" (mean, sd), "triangular" (a = min, b = mode, c = max), "uniform" (min, max) or "pert" (a, b, c, the Beta-PERT distribution). Sampled durations are truncated at zero. Productivity multipliers must use a bounded type (triangular, uniform or PERT) with a positive minimum.

References

Damnjanovic, Ivan, and Kenneth Reinschmidt. Data analytics for engineering and construction project risk management. Cham, Switzerland: Springer, 2020.

Kolisch, Rainer. Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research 90.2 (1996): 320-333.

Examples

activities <- data.frame(
  id = c("A", "B", "C", "D"),
  duration = c(3, 5, 4, 2)
)
links <- data.frame(
  source = c("A", "A", "B", "C"),
  target = c("B", "C", "D", "D"),
  type = c("FS", "SS", "FS", "FF"),
  lag = c(0, 1, 0, 1)
)
duration_dists <- list(
  B = list(type = "triangular", a = 4, b = 5, c = 9),
  C = list(type = "pert", a = 3, b = 4, c = 7)
)
resources <- data.frame(id = "crew", capacity = 1, rate = 1000)
assignments <- data.frame(
  activity = c("B", "C"), resource = "crew", units = 1
)
risks <- list(
  list(
    id = "Late permit", prob = 0.3, activities = "A",
    impact = list(type = "uniform", min = 1, max = 3)
  )
)
proj <- project_schedule(activities, links,
  duration_dists = duration_dists, resources = resources,
  assignments = assignments, risks = risks, time_unit = "days"
)
proj
#> Project Schedule
#> Activities: 4   Links: 4   Resources: 1   Risks: 1 
#> Time unit: days
#> 
#>  id duration       driver predecessors
#>   A        3        fixed             
#>   B        5 distribution            A
#>   C        4 distribution        ASS+1
#>   D        2        fixed     B, CFF+1