Draws the activity-on-node network left to right, layered by longest path
from the start. Activities on the deterministic critical path (see cpm())
and the links between them are drawn in red. Link types other than
finish-to-start, and non-zero lags, are labelled on the edge.
Usage
# S3 method for class 'pra_schedule'
plot(x, main = NULL, node_cex = 3, label_cex = 0.7, ...)Arguments
- x
An object of class
"pra_schedule".- main
Optional plot title.
- node_cex, label_cex
Node symbol and label sizes.
- ...
Additional arguments passed to
graphics::plot().
Examples
proj <- project_schedule(
data.frame(id = c("A", "B", "C", "D"), duration = c(3, 5, 4, 2)),
data.frame(
source = c("A", "A", "B", "C"), target = c("B", "C", "D", "D"),
type = c("FS", "SS", "FS", "FS"), lag = c(0, 1, 0, 0)
)
)
plot(proj)