Draws the activity-on-node network left to right, layered by longest path from the start. Activities on the deterministic critical path (see cpm()) and the links between them are drawn in red. Link types other than finish-to-start, and non-zero lags, are labelled on the edge.

Usage

# S3 method for class 'pra_schedule'
plot(x, main = NULL, node_cex = 3, label_cex = 0.7, ...)

Arguments

x

An object of class "pra_schedule".

main

Optional plot title.

node_cex, label_cex

Node symbol and label sizes.

...

Additional arguments passed to graphics::plot().

Value

Invisibly returns x.

Examples

proj <- project_schedule(
  data.frame(id = c("A", "B", "C", "D"), duration = c(3, 5, 4, 2)),
  data.frame(
    source = c("A", "A", "B", "C"), target = c("B", "C", "D", "D"),
    type = c("FS", "SS", "FS", "FS"), lag = c(0, 1, 0, 0)
  )
)
plot(proj)