Summarize critical path method results.
Usage
# S3 method for class 'cpm'
summary(object, ...)Value
An object of class "summary.cpm", a list with the project finish,
deterministic cost, the critical path, the number of critical activities,
the number of near-critical activities (total float within 10% of the
project duration), and the total and maximum float (NA when leveled).
Examples
proj <- project_schedule(
data.frame(id = c("A", "B", "C"), duration = c(2, 3, 1)),
data.frame(source = c("A", "A"), target = c("B", "C"))
)
summary(cpm(proj))
#> Critical Path Method Summary
#> ----------------------------
#> Project finish: 5 periods
#> Deterministic cost: 0
#> Critical activities: 2 of 3
#> Near-critical activities (float <= 10% of duration): 0
#> Maximum total float: 2 periods
#> Critical path: A -> B