Summarize critical path method results.

Usage

# S3 method for class 'cpm'
summary(object, ...)

Arguments

object

An object of class "cpm".

...

Additional arguments (not used).

Value

An object of class "summary.cpm", a list with the project finish, deterministic cost, the critical path, the number of critical activities, the number of near-critical activities (total float within 10% of the project duration), and the total and maximum float (NA when leveled).

Examples

proj <- project_schedule(
  data.frame(id = c("A", "B", "C"), duration = c(2, 3, 1)),
  data.frame(source = c("A", "A"), target = c("B", "C"))
)
summary(cpm(proj))
#> Critical Path Method Summary 
#> ----------------------------
#> Project finish: 5 periods 
#> Deterministic cost: 0 
#> Critical activities: 2 of 3 
#> Near-critical activities (float <= 10% of duration): 0 
#> Maximum total float: 2 periods 
#> Critical path: A -> B