Print a schedule risk analysis summary.
Usage
# S3 method for class 'summary.sra'
print(x, ...)Examples
proj <- project_schedule(
data.frame(id = c("A", "B"), duration = c(2, 3)),
data.frame(source = "A", target = "B"),
duration_dists = list(B = list(type = "triangular", a = 2, b = 3, c = 6))
)
print(summary(sra(proj, num_sims = 500)))
#> Schedule Risk Analysis Summary
#> ------------------------------
#> Iterations: 500
#>
#> Finish (periods)
#> Deterministic: 5 (probability of meeting it: 27.4%)
#> Mean: 5.618 SD: 0.8278 CV: 0.1473
#> 5% 10% 25% 50% 75% 80% 90% 95%
#> 4.398 4.548 4.951 5.581 6.150 6.346 6.764 7.132
#>
#> Activities (by cruciality)
#> id mean_duration mean_finish finish_p90 criticality sensitivity cruciality ssi
#> B 3.618 5.618 6.764 1 1 1 1
#> A 2.000 2.000 2.000 1 NA NA NA