Calculates the To-Complete Performance Index (TCPI), which indicates the cost performance required on remaining work to meet a target (BAC or EAC). TCPI > 1 means efficiency must improve; TCPI < 1 means efficiency can decrease.
Arguments
- bac
Budget at Completion (BAC) (total planned budget).
- ev
Earned Value.
- ac
Actual Cost.
- target
The target to calculate TCPI against. Either "bac" (default) to meet original budget, or "eac" to meet revised estimate. If "eac", the eac parameter must be provided.
- eac
Estimate at Completion. Required when target = "eac".
Examples
bac <- 100000
ev <- 35000
ac <- 63000
# TCPI to complete within original budget
tcpi_bac <- tcpi(bac, ev, ac)
cat("TCPI (to meet BAC):", round(tcpi_bac, 2), "\n")
#> TCPI (to meet BAC): 1.76
# TCPI to complete within revised estimate
eac <- 120482
tcpi_eac <- tcpi(bac, ev, ac, target = "eac", eac = eac)
cat("TCPI (to meet EAC):", round(tcpi_eac, 2), "\n")
#> TCPI (to meet EAC): 1.13