This function creates a base R plot of a fitted sigmoidal model with the original data points, fitted curve, and optional confidence bounds.

Usage

plot_sigmoidal(
  fit,
  data,
  x_col,
  y_col,
  model_type,
  conf_level = NULL,
  n_points = 100,
  main = NULL,
  xlab = NULL,
  ylab = NULL,
  line_col = "red",
  ci_col = "lightblue",
  pch = 16,
  ...
)

Arguments

fit

A fitted sigmoidal model object from fit_sigmoidal.

data

The original data frame used to fit the model.

x_col

The name of the x (time) column in the data.

y_col

The name of the y (completion) column in the data.

model_type

The type of model (pearl, gompertz, or logistic).

conf_level

Optional confidence level for confidence bounds (e.g., 0.95 for 95%). If NULL (default), no confidence bounds are plotted.

n_points

Number of points to use for the fitted curve (default 100).

main

Plot title. If NULL, a default title is generated.

xlab

X-axis label. If NULL, uses x_col.

ylab

Y-axis label. If NULL, uses y_col.

line_col

Color for the fitted curve (default "red").

ci_col

Color for the confidence band (default "lightblue").

pch

Point character for data points (default 16).

...

Additional arguments passed to plot().

Value

Invisibly returns the predictions data frame.

References

Damnjanovic, Ivan, and Kenneth Reinschmidt. Data analytics for engineering and construction project risk management. No. 172534. Cham, Switzerland: Springer, 2020.

Examples

# Set up a data frame of time and completion percentage data
data <- data.frame(time = 1:10, completion = c(5, 15, 40, 60, 70, 75, 80, 85, 90, 95))

# Fit a logistic model to the data.
fit <- fit_sigmoidal(data, "time", "completion", "logistic")

# Plot the fitted model
plot_sigmoidal(fit, data, "time", "completion", "logistic")


# Plot with 95% confidence bounds
plot_sigmoidal(fit, data, "time", "completion", "logistic", conf_level = 0.95)


# Customize the plot
plot_sigmoidal(fit, data, "time", "completion", "logistic",
  conf_level = 0.95,
  main = "Project Completion Forecast",
  xlab = "Time (weeks)",
  ylab = "Completion (%)",
  line_col = "blue",
  ci_col = "lightgray"
)